Solution ID: prim14457 |
How to show cross project relationships in Activity Network |
Status: Reviewed |
Version(s): 3.5, 3.5.1, 4.0, 4.0, 4.1, 4.1, 5.0 |
Problem: | How to show interproject relationships in an Activity Network layout |
Problem: | How to show cross project relationships in Activity Network |
Problem: | How to show relationships between activities in different projects in Activity Network layout |
Problem: | Can you display inter project relationships within the Activity Network? |
Problem: | Activity Network Diagram does not show inter project relationships |
Fix: | 1. Open all applicable projects in Project Management. 2. Group and sort by Project or WBS. 3. Select multiple projects on the left side of the view (use Ctrl+click or Shift+click). If the relationship lines are still not visible, click on View, Activity Network, Activity Network Options, and select the Activity Network Layout tab. Check the option, ”Adjust to show all relationships”. |