Solution ID: prim18898 |
How is the timescale for project website layouts determined? |
Status: Reviewed |
Version(s): 3.5, 3.5.1, 3.5.1, 4.0, 4.0, 4.1, 4.1, 5.0, 6.0, 6.1, 6.2, 6.2.1, 7.0 |
From Primavera OCP
Problem: | How is the timescale for project website layouts determined? |
Problem: | How to save specific timescale dates when publishing a project website. |
Fix: | Publish Project Website sets the timescale start to earliest Start Date of the open projects. The timescale end is set to beyond the latest Early Finish of the open projects. There are two options to use specific dates when using Publish Project Website.
|