prim19005:Updating Activity Expenses is not working as expected when using the Subtract Rule

Solution ID: prim19005
Updating Activity Expenses is not working as expected when using the Subtract Rule
Status: Reviewed
Version(s): 4.0, 4.1



Problem:

Using the Subtract Rule and an Activity Expense , At Complete Cost is updated instead of Remaing Costs when a user sets Actual Cost to zero.


EXAMPLE:


1. At the Project Level, set Subtract Actual from At Complete rule on the Calculations tab


2. Create an activity and assign an expense  


3. Put an Actual Cost > 0 on the Expense


4. Notice Remaing Costs = At Complete Cost – Actual Cost  


 5. Now reset Actual Cost = 0


6. Notice At Complete is updated instead of Remaining


NOTE: This will only occur when there is an Actual Start and/or Actual Finish on the activity. If the activity has not Started, then the Subtract Rule will still be enforced when a user resets Actual Cost = 0.


 

Fix: This known problem in Project Management is fixed in version 4.1 Service Pack 3 and Primavera Contractor version 4.1 Service Pack 3.

To download the latest Service Pack, see:
Solution ID PRIM29780:  Primavera Project Management Version 4.1 Service Pack 4 (SP4)
Solution prim24657: Contractor version 4.1 Service Pack 3


Viewing all articles
Browse latest Browse all 209

Trending Articles