PART I: In the TARGET PROJECT, perform the following steps:
1. Create a Resource/Cost Custom Data Item called “TGBC” to store the target BC. To do this, go to Data, Custom Data Items, Resource/Cost. Add a CDI with the following specifications:
![]()
2. Run a Global Change, to populate TGBC with the BC of the target project. To do this, go to Tools, Global Change. Add a new Global Change with the following specifications:
Then: TGBC EQ BC
![]()
3. Export the Activity ID, Resource, Cost Account and Resource Custom Data Items to a .WK1 file. To do this go to Tools, Project Utilities, Export. Create a new export with the following specifications:
![]()
PART II: In the CURRENT PROJECT, perform the following steps:
1. Create the same custom data item in the current project that you created in target project in Part I. To do this, go to Data, Custom Data Items, Resource/Cost. Add a CDI with the following specifications:
![]()
NOTE: The format of the Custom Data Item Dictionary MUST be the same in both the target project and current project. If there are other CDIs in the dictionary, make sure each entry exists in both dictionaries and that they all appear in the same order.
2. Import the .WK1 file created in Part I:3 above. To do this, go to Tools, Project Utilities, Import. Specify the path and filename of the .WK1 file to be imported. When this is complete, the CDI TGBC in the current project should be populated the BC values of the target project.
3. Create another Resource/Cost Custom Data Item called TBCV (Target Budget Cost Variance). To do this, go to Tools, Data, Custome Data Items, Resource/Cost. Add a CDI with the following specifications:
![]()
3. Run a Global Change, to populate TBCV with the difference between BC and TGBC (Target BC). To do this, go to Tools, Global Change. Add a new Global Change with the following specifications:
Then: TBCV EQ BC - TGBC
![]()
4. Add the column TBCV to your layout to display the difference between BC and Target BC.
|