prim24580:How are P3 constraints converted in Project Management?

$
0
0
Solution ID: prim24580
How are P3 constraints converted in Project Management?
Status: Reviewed
Version(s): 3.1, 4.0, 4.1, 5.0



Problem:  How are P3 constraints converted in Project Management?
Problem: What are the equivalent (P3) constraints in Project Management? 
Problem: P3 constraint mapping
Fix:

Below is a table outlining how constraints are mapped from P3 3.1 to Project Management:





































P3 Constraint Type


Project Management module


Constraint Type


Early Start (start no earlier than)


Start On or After


Late Start (start no later than)


Start On or Before


Early Finish (finish no earlier than)


Finish On or After


Late Finish (finish no later than)


Finish On or Before


Start On


Start On


Expected Finish


Expected Finish Date


Mandatory Start


Mandatory Start


Mandatory Finish


Mandatory Finish


Zero Total Float


Not Converted


Zero Free Float


As Late As Possible