Solution ID: prim14831 |
When copying activities from a project with read only access to a project with read write access, the activities are copied back into the project with read only access. |
Status: Reviewed |
Version(s): 3.x, 4.0, 4.1 |
Problem: | When copying activities from a project with read only access to a project with read write access, the activities are copied back into the project with read only access. Steps to duplicate:
|
Fix: | This is a known problem in Project Manager/Project Management has been corrected in version 4.1 Service Pack 2. To download the latest Service Pack, see: |