Information |
Calculation / Comments |
Summary Date |
The date the project was last summarized. |
The project is x% complete. |
Perf % Complete = BCWP / BAC
|
It is $X or X% over budget and
It is $X or X% under budget and
It is on budget and |
$X = CV = BCWP ?Actual Cost
X% = CV / BCWP
If $X < 0, then it is over
If $X > 0, then it is under
If $X = 0, then it is on budget |
X days or X% behind schedule.
X days or X% ahead of schedule.
on schedule. |
X days = BL Dur * Perf% Complete – BL Dur * Sched % Complete
X% = # above / Baseline Duration
If X < 0, then it is behind
If X > 0, then it is ahead
If X = 0, then it is on schedule |
The finish date will be XX/XX/XX |
The calculated finish date of the project. (re_end_date) |
or X days late.
or X days early.
or on time. |
X = re_end_date – base_end_date
If X < 0, then it is late
If X > 0, then it is early
If X = 0, then it is on schedule |
The total cost will be between $X or X% over budget and
The total cost will be between $X or X% under budget and
The total cost will be between $X or on budget and |
$X = BAC / CPI
X% = # above – BAC
BAC
If $X < 0, then it is over budget
If $X > 0, then it is unde budget
If $X = 0, then it is on budget |
$X or X% over budget.
$X or X% under budget.
$X or on budget. |
$X =BAC
(CPI * SPI)
X% = # above – BAC
BAC
If value < 0, then it is over budget
If value > 0, then it is under budget
If value = 0, then it is on budget |