prim18513:Executive Summary calculations in myPrimavera

Solution ID: prim18513
Executive Summary calculations in myPrimavera
Status: Reviewed
Version(s): 4.0, 4.1, 5.0



Problem: Executive Summary calculations in myPrimavera
Fix:



























Information


Calculation / Comments


Summary Date


The date the project was last summarized.


The project is x% complete.


Perf % Complete = BCWP / BAC



It is $X or X% over budget and


It is $X or X% under budget and


It is on budget and


$X = CV = BCWP ?Actual Cost


X% = CV / BCWP


If $X < 0, then it is over


If $X > 0, then it is under


If $X = 0, then it is on budget


X days or X% behind schedule.


X days or X% ahead of schedule.


on schedule.


X days = BL Dur * Perf% Complete – BL Dur * Sched % Complete


X% = # above / Baseline Duration


If X < 0, then it is behind


If X > 0, then it is ahead


If X = 0, then it is on schedule


The finish date will be XX/XX/XX


The calculated finish date of the project. (re_end_date)


or X days late.


or X days early.


or on time.


X = re_end_date – base_end_date


If X < 0, then it is late


If X > 0, then it is early


If X = 0, then it is on schedule


The total cost will be between $X or X% over budget and


The total cost will be between $X or X% under budget and


The total cost will be between $X or on budget and


$X = BAC / CPI


X% = # above – BAC


BAC


If $X < 0, then it is over budget


If $X > 0, then it is unde budget


If $X = 0, then it is on budget


$X or X% over budget.


$X or X% under budget.


$X or on budget.


$X =BAC


(CPI * SPI)


X% = # above – BAC


BAC


If value < 0, then it is over budget


If value > 0, then it is under budget


If value = 0, then it is on budget